The Dominick's cooling tower was found down by on-site engineers. Green's technician team was sent to troubleshoot, and saw Cell #2 inoperable. All the components inside, including the motor, shaft, fan blades, belt, and pulleys were worn out and in need of replacement.
All of the old components were removed, and new equipment was ordered and installed. Technicians ran the factory start-up sequence, and had the tower fully operational before the hot summer weather.